Energy Efficiency Projects

  
  
  
  
  
  
Description
  
  
  
ALBANY CITY SCHOOLSAlbany City School District - Phase V (ARRA)ALBANYCentral
$6,088,978.52
1,900
Replacement of three boilers and a DHW heater, installation of two 75 kW CHP units and a pool cover, optimization of chiller plant controls, and upgrades to AHUs, lighting, and the pool heating and ventilation s
In Development2015
ALBANY, COUNTY OFAlbany County - Ph.2 - Times Union Ctr. Boiler/Chiller/HVACALBANYCentral
$3,579,716.00
1,142
Upgrade lighting, boilers, HVAC systems and controls.
In Development2015
CITY OF NEW YORKNYC DOC - Rikers Island - Central Chiller Plant - Construction Ph.2QUEENSSoutheastern
$6,792,416.52
5,159
Construction Phase 2: Installation of a central chiller plant at Rikers Island. A 960 ton electrical centrifugal chiller, a 1000 ton steam absorption chiller, and a 700kW back-pressure steam turbine will be installed.
In Development2015
CITY OF NEW YORKCo-op City Public Schools CampusBRONXSoutheastern
$15,237,533.76
1,896
Replacement of chiller, AHU rehab, and lighting upgrade.
In Development2015
CITY OF NEW YORKIS-383K (Philippa Schuyler School)KINGSSoutheastern
$2,865,314.35
255
Upgrade lighting, wireless vacancy sensors, and premium efficiency motors.
In Development2015
CITY OF NEW YORKPS-78X (Anne Hutchinson School)BRONXSoutheastern
$1,773,512.93
219
Upgrade lighting, lighting controls, and steam system.
In Development2015
CITY OF NEW YORKNYC DOE Schools Solar PV (Phase 1B)KINGSSoutheastern
$2,156,530.29
296
Design, permitting, installation, start-up, and commissioning of 477.63 kW of rooftop mounted self-ballasted solar PV systems across four NYC schools: PS-224K, PS-302K, PS-324K and PS-445.
In Development2015
CITY OF NEW YORKNYC Dept of Parks - Central Park Zoo - LightingNEW YORKSoutheastern
$152,745.34
81
Combination of measures  .
In Development2015
CITY OF NEW YORKNYC HHC - Woodhull Hospital Center - ComprehensiveKINGSSoutheastern
$9,462,885.49
2,359
Installation of lighting & lighting controls, boiler burner   replacement, steam traps, EMS  upgrades and gan coil unit variable speed controller.
In Development2015
CITY OF NEW YORKNYPD - Old 41st Police Precinct - Lighting & SensorsBRONXSoutheastern
$162,236.90
109
Installation of lighting and occupancy sensors. 
In Development2015
CITY UNIVERSITY OF NEW YORKCUNY Internet Metering - NYC College of TechnologyNEW YORKSoutheastern
$359,457.00
212
Installation of internet metering system at NYC College of   Technology. 
In Development2015
FONDA FULTONVILLE CSDFonda-Fultonville Central School DistrictMONTGOMERYCentral
$1,144,098.88
416
Installation of high-efficiency lighting and controls, a pool cover, and an 80 kW photovoltaic installation.
In Development2015
LONG BEACH, CITY OFCity of Long Beach - Lighting & HVAC UpgradesNASSAUSoutheastern
$1,543,322.78
456
Installation of high-efficiency lighting and controls at the public works building and ice rink and includes upgrades of street lighting to LED technology.
In Development2015
MOUNT VERNON CSDCity of Mount Vernon - School District Energy AuditsWESTCHESTERSoutheastern
$87,253.80
0
Energy Audits at 18 Mount Vernon School Faciliities 
In Development2015
MTA - Metropolitan Transportation AuthorityTBTA - Verrazano Bridge Service Building and Maintenance ShopsRICHMONDSoutheastern
$416,409.43
178
Upgrade lighting and install energy efficient boilers. 
In Development2015
MTA - Metropolitan Transportation AuthorityMetro North - GCT Exterior LightingNEW YORKSoutheastern
$106,236.47
55
Upgrade exterior lighting with LED at Grand Central Terminal.
In Development2015
MTA - Metropolitan Transportation AuthorityNYCT - Manhattanville Bus Depot - LightingNEW YORKSoutheastern
$1,509,147.21
939
Upgrade lighting. 
In Development2015
MTA - Metropolitan Transportation AuthorityNYCT - West Farms Bus Depot LightingBRONXSoutheastern
$838,605.31
543
Upgrade HID high bay lights in the facility
In Development2015
MTA - Metropolitan Transportation AuthorityNYCT - College Point Bus Depot Exterior LED LightingQUEENSSoutheastern
$155,294.88
82
Upgrade outdoor parking lights with LED lights 
In Development2015
MTA - Metropolitan Transportation AuthorityNYCT - Central Electronics Shop Comprehensive ProjectQUEENSSoutheastern
$313,150.40
192
Upgrade lighting and HVAC system in the building 
In Development2015
NORTHEAST CSDWebutuck CSDDUTCHESSSoutheastern
$934,987.74
348
Installation of high-efficiency lighting and controls at the high school and installation of high-efficiency lighting and controls and a 20.25 kW PV system at the elementary school.
In Development2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - 26th Ward WWTP - Lighting StudyKINGSSoutheastern
$240,393.00
0
Feasibility Study: Installation of sample lighting throughout   various plant locations. The findings of the study will be used to identify the fixtures to be installed that will increase energy efficiency. 
In Development2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - SOGR/ECM Planning Task 1 - Wards Island WWTPNEW YORKSoutheastern
$89,526.00
0
Integrate DEP's 10-year State of Good Repair (SOGR) capital project plan for WWTPs with energy conservation measures (ECMs) identified by previously-prepared energy audits, and identify any additional opportunities to save energy.
In Development2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Hunts Point Centrifuge Replacement - Ph.1 DesignBRONXSoutheastern
$1,585,264.68
0
Upgrade dewatering centrifuges with energy efficient equipment. Phase I will be for the 30% design development   for the installation of 16 energy efficient centrifuges. 
In Development2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - 26th Ward Centrifuge Replacement - Ph.1 Design and Equipment PurchaseKINGSSoutheastern
$1,585,264.68
0
Upgrade dewatering centrifuges with energy efficient equipment. Phase I will be for the 30% design development for the installation of 16 energy efficient centrifuges for the 26th Ward WWTP 
In Development2015
ORCHARD PARK FIRE DISTRICTOrchard Park Fire DistrictERIEWestern
$113,093.45
24
Installation of lighting retrofits and controls, upgrades to HVAC systems.
In Development2015
PORT AUTHORITY OF NY AND NJPort Authority - Advanced Metering Infrastructure - Phase IIIA Construction JFKMULTIPLEMultiple
$4,000,000.00
0
Installation of new smart meters, wiring, and devices to transmit meter data automatically to the MDSP Platform (Phase II) of the AMI Program. 
In Development2015
ROCHESTER, CITY OFCity of Rochester - Phase III - Blue Cross ArenaMONROECentral
$869,090.50
172
Upgrade make-up air handling units, the BMS, and lighting and installation of controls and de-stratification fans.
In Development2015
State of New York (OGS, SUNY, all state agencies)NYS DOCCS - Energy Master Plan - Phase IIIALBANYCentral
$591,552.90
0
Development of an Energy Master Plan for the following DOCCS facilities: Greene, Washington, Ulster, Shawangunk, Great Meadow, Coxsackie, Wallkill, and Eastern in support of the Build Smart NY initiative.
In Development2015
State of New York (OGS, SUNY, all state agencies)OGS - 55 Hanson Place - Lighting and Chiller UpgradeKINGSSoutheastern
$2,249,739.48
534
Upgrade building lighting and replace (2) 500 ton AC chillers.       
In Development2015
State of New York (OGS, SUNY, all state agencies)OGS ESP - Compressor Replacement/VFDALBANYCentral
$1,556,958.89
422
Replacement of the main plant air compressor with a new compressor with a variable frequency drive and installation of a new compressor at the Sheridan Avenue steam plant. 
In Development2015
State of New York (OGS, SUNY, all state agencies)NYS Executive Mansion LEED Re-Certification - CIALBANYCentral
$86,310.00
91
Re-certification of the LEED status, an ASHRAE Level 1 Audit of the facility, the development of a retro-commissioning plan. Customer implemented, NYPA financed.
In Development2015
State of New York (OGS, SUNY, all state agencies)NYS OMH - New York Psychiatric Institute- Free Cooling Heat Exchanger - CINEW YORKSoutheastern
$540,059.34
0
Installation of plate heat exchangers to utilize cooling tower water for free cooling during the winter months. Customer Implemented, NYPA financed.
In Development2015
State of New York (OGS, SUNY, all state agencies)NYS OMH - Pilgrim Psych. Ctr. - Phase II - Boiler Controls & Outdoor LightingSUFFOLKSoutheastern
$1,096,907.14
466
Installation of new linkageless boiler controls. This new control system will allow parallel positioning of the existing 5 boilers to optimize matching load conditions.
In Development2015
State of New York (OGS, SUNY, all state agencies)SUNY Maritime - Energy Master PlanBRONXSoutheastern
$102,960.00
0
Development of an Energy Master Plan for the SUNY Maritime Campus located in Throgs Neck, NY in support of the Build Smart NY initiative. 
In Development2015
State of New York (OGS, SUNY, all state agencies)SUNY Purchase - Ph.IX - Cooling Tower ReplacementWESTCHESTERSoutheastern
$9,214,408.78
359
Replacement of existing 1991 BAC Cooling Towers and associated pumping and piping system, with new cooling towers, cooling tower fans and condenser water pumps. 
In Development2015
State of New York (OGS, SUNY, all state agencies)SUNY Brockport - Phase VIMONROECentral
$3,682,211.00
831
Replacement and upgrades to boilers, installation of lighting controls, and enhancements to chiller loops.
In Development2015
State of New York (OGS, SUNY, all state agencies)SUNY Alfred State - Energy Master PlanALLEGANYWestern
$200,257.45
0
Development of a campus-wide Energy Master Plan in support of the Build Smart NY initiative. This EMP will include benchmarking, a letter report, an ASHRAE Level 2 audit, and thermal imaging.
In Development2015
University of Albany FoundationUniversity at Albany Bioscience Dev. Corp. - Phase I - TransformersRENSSELAERCentral
$2,632,628.02
865
Replacement of the existing switchgear with a high-tension 34.5 switchgear and the transformer with a more efficient unit, installation of a generator to use for demand peak shaving.
In Development2015
UTICA, CITY OFCity of Utica - LED Lighting ESPCONEIDACentral
$1,000,000.00
0
Upgrade LED lighting at various sites throughout the city of Utica. Customer Implemented.
In Development2015
WESTCHESTER, COUNTY OFWC Valhalla Campus - DPS Armory Building - BoilerWESTCHESTERSoutheastern
$1,258,570.50
59
Installation of energy efficient boiler and domestic hot water system.
In Development2015
CITY OF NEW YORKNYC DOC - Rikers Island - Central Chiller Plant - 100% DesignQUEENSSoutheastern
$2,650,967.00
0
Phase I. Develop 100 % design document for the installation of a 2,000 ton central chiller plant with auxiliary equipment to support air-conditioning loads for several buildings and inlet cooling needs for the Co-Generation Plant. 
In Progress2015
CITY OF NEW YORKNYC DOC - Rikers Island Co-Gen - Ph.3 - Prepurchase of Major EquipmentQUEENSSoutheastern
$20,935,859.99
0
Purchase of gas turbines, heat recovery steam generators, gas compressors and electric switch gear for the implementation of the Rikers Island Cogen project. 
In Progress2015
CITY OF NEW YORKNYC DOC - Rikers Island Co-Gen - Ph.5 - Construction Ph.2QUEENSSoutheastern
$34,113,237.26
22,083
Rikers Island Co-Gen Ph. 5 includes the second phase of construction costs to build a cogeneration plant.
In Progress2015
CITY OF NEW YORKNYC DOC - Rikers Island Co-Gen - Ph.4 - Construction Ph.1QUEENSSoutheastern
$56,630,490.00
0
Construction of a 15MW cogeneration plant integrated into the existing heating systems. Phase IV (final) of the Rikers Island Cogeneration plant entails the actual construction of the plant. 
In Progress2015
CITY OF NEW YORKNYC DOC - Rikers Island - Central Chiller Plant - Construction Ph.1QUEENSSoutheastern
$20,325,259.60
0
Construction Phase 1: Installation of a central chiller plant at Rikers Island. A 960 ton electrical centrifugal chiller, a 1000 ton steam absorption chiller, and a 700kW back-pressure steam turbine will be installed.
In Progress2015
CITY OF NEW YORKDCLA - Bronx Zoo - MTHW Loop Replacement- Ph II (30% - Final Design)BRONXSoutheastern
$942,609.70
0
Design only CIC for the cost of 30% to Final Design of the MTHW Cogen loop replacement.
In Progress2015
CITY OF NEW YORKDCLA - Staten Island Zoo / Staten Island Museum - Lighting & SensorsRICHMONDSoutheastern
$280,619.84
110
Upgrade the lighting system in both the Staten Island Zoo and Staten Island Museum.
In Progress2015
CITY OF NEW YORKPS-721M (Manhattan Occupational Training Ctr)NEW YORKSoutheastern
$1,779,664.84
272
Installation of lighting, lighting controls, steam traps, and DDC for night setback. 
In Progress2015
CITY OF NEW YORKNYC DOE Schools Solar PV (Phase 1A)KINGSSoutheastern
$4,536,727.62
659
Installation of 1100KW of solar PV at three NYC schools: PS-455K, PS-505K and PS-69R. DCAS DOE Solar PV NYSERDA granted project.
In Progress2015
CITY OF NEW YORKPS-21X (Philip H. Sheridan)BRONXSoutheastern
$1,484,912.49
137
Installation of energy efficient lighting, occupancy sensors, remove asbestos/PCBs. 
In Progress2015
CITY OF NEW YORKPS-307K (Daniel Hale Williams School)KINGSSoutheastern
$2,070,176.56
191
Upgrade lighting and install occupancy sensors. Remove asbestos/PCBs. 
In Progress2015
CITY OF NEW YORKNYC Dept of Parks - 5-Boro ComplexNEW YORKSoutheastern
$1,740,050.11
308
Installation of two new energy efficient boilers and ancillary equipment and controls. 
In Progress2015
CITY OF NEW YORKCity of New York - End Use Metering ServicesNEW YORKSoutheastern
$319,613.50
0
Installation of end-use monitoring program for continuous real-time monitoring and end-use metering. Pilot project at 10 City of New York sites. Design, install,collect, display and host end-use and whole facility metering.
In Progress2015
CITY OF NEW YORKCo-op City Public Schools Campus - LightingBRONXSoutheastern
$3,086,807.96
243
Upgrade lighting and installation of occupancy sensor.
In Progress2015
CITY OF NEW YORKCity of New York - Energy & RCx Audits (Group 7 FY14)NEW YORKSoutheastern
$2,004,190.36
0
Perform Energy and Retro-Commissioning Audits.
In Progress2015
CITY OF NEW YORKBrooklyn Cruise Terminal - Lighting and HVAC UpgradeKINGSSoutheastern
$987,396.58
499
Comprehensive efficiency upgrade of the BCT including Lighting and HVAC.
In Progress2015
CITY OF NEW YORKNYC HHC - Elmhurst Hospital CenterQUEENSSoutheastern
$28,462,000.80
8,541
Boiler replacement, air handling unit upgrades, building management system, lighting, occupancy sensors, underground tank removal and replacement, removal of asbestos and PCBs. 
In Progress2015
CITY OF NEW YORKNYC HHC - Coney Island Hospital - Boiler UpgradeKINGSSoutheastern
$9,933,724.00
3,593
Upgrade boiler system with energy efficient equipment at Coney Island Hospital. Amended original scope on July 2013 to raise new boilers and associated equipment above the FEMA designated 100-year flood line. 
In Progress2015
CITY OF NEW YORKNYC HHC - Metropolitan Hospital CenterNEW YORKSoutheastern
$34,349,704.52
6,030
Boiler replacement, air handling unit upgrades, buiding management system, lighting, occupancy sensors, underground tank removal and replacement, removal of asbestos and PCBs. 
In Progress2015
CITY OF NEW YORKNYC HHC - Lincoln Medical Center - ASHRAE Level II AuditBRONXSoutheastern
$128,000.00
0
Conduct ASHRAE Level II audit at the facility
In Progress2015
CITY OF NEW YORKNYPD - 69th PrecinctKINGSSoutheastern
$1,065,669.39
83
Installation of energy efficient chiller and boiler at the NYPD 69th Precinct: replacement of two chillers (20-ton each) with a single forty ton high efficiency air-cooled chiller. Replace existing boiler with a high efficiency boiler.   
In Progress2015
CITY OF NEW YORKNYPD - One Police Plaza - Police Headquarters (ARRA)NEW YORKSoutheastern
$18,156,991.83
4,584
Installation of high efficiency lighting, lighting controls, upgrade BMS and air handling units controls, refurbish air handling units, optimize chiller plant, upgrade the cooling equipment used in the data center to energy efficient. 
In Progress2015
CITY UNIVERSITY OF NEW YORKCUNY Internet Metering - Medgar Evers College - Technology UpgradeNEW YORKSoutheastern
$392,593.00
173
Installation of "Data Gathering" devices which connect to the utility meter and then upload the energy data to an internet server provided by the customer.
In Progress2015
CITY UNIVERSITY OF NEW YORKCUNY Bronx C.C. - Ph.3: Utility Upgrade - CHW and HW DistributionBRONXSoutheastern
$22,000,000.50
0
Installation of a high efficiency centralized chiller plant and power efficiency upgrade. This phase will include the continued installation of underground utilities throughout the campus.
In Progress2015
CITY UNIVERSITY OF NEW YORKCUNY Internet Metering - Hunter CollegeNEW YORKSoutheastern
$465,536.00
611
Installation of data gathering equipment that will interface with the electric, gas and steam utility meters. The energy data will be captured and displayed on a web based server for monitoring as well as data storage.
In Progress2015
CITY UNIVERSITY OF NEW YORKCUNY Internet Metering - CCNYNEW YORKSoutheastern
$499,338.00
850
Installation and commissioning of metering devices that will allow CUNY to remotely monitor energy usage and evaluate trends and savings opportunities.
In Progress2015
CITY UNIVERSITY OF NEW YORKCUNY Internet Metering - Software IntegrationNEW YORKSoutheastern
$423,789.00
774
Software Integration of Existing Utility Meters at CUNY Senior Campuses. This is a real-time, internet-based, energy monitoring system to help monitor energy consumption,   identify energy savings opportunities, and comply with EO88 at CUNY facilities.
In Progress2015
CORNWALL CSDCornwall Schools - Lighting & HVACORANGESoutheastern
$5,459,864.02
895
Upgrade lighting and lighting controls, replace boiler, and HVAC systems with energy efficient equipment, upgrades and fuel conversion from oil to natural gas boilers and upgrade pool dehumidification system with energy efficient equipment.
In Progress2015
HOOSICK FALLS CSDHoosick Falls CSD - Wood Pellet Boiler ESPCRENSSELAERCentral
$298,269.39
388
Installation of a wood pellet boiler and a silo for the pellets and the moving of the school's generator to another location. Customer Implemented.
In Progress2015
LOCKPORT, CITY OFCity of Lockport - Lighting & HVACNIAGARAWestern
$222,946.17
87
Installation of energy efficient lighting and conversion of DHW heating from electric to natural gas.
In Progress2015
MONROE, COUNTY OFMonroe County Correctional Facility - CIMONROECentral
$1,497,201.64
448
Installation of DDC controls, lighting retrofits, energy efficient motors, a chiller, hot water and chilled water pumps, and VFDs. Customer Implemented.
In Progress2015
MONROE, COUNTY OFMonroe County Mill Seat Landfill Gas Generation Ph.III - CIMONROECentral
$10,009,674.64
12,967
Installation of four Caterpillar 3516 Generator Sets rated at 800 kW each and all associated equipment. The generators will produce approximately 21,024,000 kWh annually at 75% capacity.
In Progress2015
MONROE, COUNTY OFMonroe County Civic Center - CIMONROECentral
$15,243,099.23
3,616
Installation of high efficiency lighting, chilled water control valves, controls for HVAC systems, premium efficiency motors, and a micro-steam turbine. Customer Implemented.
In Progress2015
MTA - Metropolitan Transportation AuthorityMetro North - North White Plains Yard HVAC UpgradeWESTCHESTERSoutheastern
$2,185,973.82
1,279
Installation of a new high efficiency HVAC, boilers, BMS system, VFD motors with control valves, new programmable thermostats, new steam traps, and balance VAVs. 
In Progress2015
MTA - Metropolitan Transportation AuthorityMetro North - Mt. Vernon Station - Electric Infrastructure for Regenerative BrakingWESTCHESTERSoutheastern
$42,894,929.00
9,201
Installation of metering equipment and electric service   improvements to allow Metro North Railroad to take advantage of regenerative braking at their Mount Vernon Bridge 23 Substation.
In Progress2015
MTA - Metropolitan Transportation AuthorityMetro North - Grand Central Terminal - Ph.IINEW YORKSoutheastern
$24,821,024.87
11,275
Phase II: Pumps/ VFDs, BMS upgrade / AHUS, steam system repairs, air compressors, chiller plant replacement, cooling tower controls, metering. Additional scope added: new cooling towers. 
In Progress2015
MTA - Metropolitan Transportation AuthorityMetro North - Grand Central Terminal - Standby GeneratorsNEW YORKSoutheastern
$19,123,463.28
0
Installation of two 2,000KW standby generators for Grand Central Terminal, associated fuel storage tank, paralleling switchgear, distribution switchgear, relays and controls, load banks, power transformers, and connection into existing SCADA system.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - 3rd Rail Heater Wireless Controls - Ph.IVNEW YORKSoutheastern
$3,041,673.85
3,618
Phase IV: Installation of a wireless control network to remotely activate 3rd rail heaters from a central location (38th Street Yard - Brooklyn).
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Coney Island Yard - Boiler ReplacementKINGSSoutheastern
$5,447,665.50
1,547
Replacement of central boiler plant with energy efficient boiler. 
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Central Station Battery Energy Storage System - CINEW YORKSoutheastern
$175,282.00
0
Installation of an advanced battery system and monitoring equipment at a central sub-station in Manhattan. Benefits   include stabilize the third rail voltage and collect regenerative   energy during the special testing using an R160 train.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Tiffany Warehouse Lighting and Rapid Roll Up DoorsBRONXSoutheastern
$501,743.49
353
Upgrade lighting and roll up doors in the facility. 
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - LED Bank of Lights Phase 2NEW YORKSoutheastern
$4,016,079.58
1,903
Replace incandescent bank of lights with LED bank of lights.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Tunnel Series LED Lighting - Ph. IVNEW YORKSoutheastern
$335,289.82
242
Furnish and Supply LED bulbs to replace existing blue incandescent and fluorescent 120v / 277v used for track disconnects in  subway tunnels.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Pelham Diesel ShopBRONXSoutheastern
$811,877.98
234
Replace lighting with high efficiency T5 and LED lights. Replace two compressors with energy efficient compressors and replace a small boiler.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Bus Depot - Rapid Roll Up Door Installation at Multiple Bus DepotsMULTIPLEMultiple
$1,412,583.01
494
Replace existing inefficient metal doors with energy efficient rapid roll up doors to reduce air infiltration.
In Progress2015
MTA - Metropolitan Transportation AuthorityNYCT - Jamaica Maintenance Shop Radiant Heating SystemQUEENSSoutheastern
$1,704,387.30
1,023
Installation of infrared heating system at Jamaica Maintenance Shop. NOTE: Pitkin Yard was removed from the scope of work due to roof issues at the facility.
In Progress2015
MTA - Metropolitan Transportation AuthorityMTA - Executive Order 88 Audits & RCx, Ph.1MULTIPLEMultiple
$904,176.00
0
Perform Energy Audits & Retro-Commissioning for the   Metropolitan Transportation Authority to meet the goals of Executive Order 88. The Energy Audits will be comprehensive in nature and will be equivalent to an ASHRAE Level II audit.
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Owl's Head WWTP - Ph.2: Improvements to the Engines Automation & Combustion SystemsKINGSSoutheastern
$30,426,945.00
8,300
This renewable project includes the energy and emissions curtailment that reduces the purchase of utility electric supply and maximize the utilization of produced digester gas and existing generation capacity at the Owls Head WPCP.
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Wards Island Dewatering Centrifuges (WI-290A) - Ph.2 and 3 Design and ConstructionNEW YORKSoutheastern
$33,182,251.00
2,628
Upgrade dewatering centrifuges with energy efficient equipment. Installation of the dewatering centrifuges pre-purchased under the Phase I CIC (ES-GSN-0575, WI-290), and other necessary equipment and systems as desig
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Wards Island Dewatering Centrifuges (PW-80) - Ph.1 Equipment PurchaseNEW YORKSoutheastern
$14,633,444.00
0
Upgrade dewatering centrifuges with energy efficient equipment. This phase I involves the pre-purchasing of the centrifuge equipment. 
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - 26th Ward Digester Upgrade - Ph.2 Design and ConstructionKINGSSoutheastern
$26,191,089.30
1,747
Upgrade the anaerobic digester gas collection system to stop leaks and improve the quality of renewable ADG gas. The gas is then used in the fuel cells for electricity production and the boiler system for heat production.
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Wards Island WWTP - Boiler/Genset and CoGen (WI-297) - Feasibility StudyNEW YORKSoutheastern
$794,855.35
0
Develop an Investment-Grade Feasibility Study that will include, but not be limited to, the evaluation of boilers, emergency generators, and a cogeneration facility at the Wards Island Water Pollution Control Plant.
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - Bowery Bay WWTP Digester Gas Improvements ADG-2 Ph.1QUEENSSoutheastern
$23,481,771.00
11,349
Upgrade existing anaerobic digester gas collection and   distribution system to provide a supply of digester gas that can be used as a renewable fuel source by the existing boilers.
In Progress2015
NYC DEPT OF ENVIRONMENTAL PROTECTIONNYC DEP - North River WPCP - Lighting Upgrade - ASHRAE Audit OnlyNEW YORKSoutheastern
$122,428.00
0
ASHRAE audit only for a plant-wide lighting upgrade. 
In Progress2015
NYPA St. Lawrence Power PlantNYPA St. Lawrence Power Project - HVAC & LightingST. LAWRENCENorthern
$4,679,225.33
4,573
Upgrade lighting and controls, HVAC systems in main and remote buildings, general mechanical operations to dam area, tunnel and gallery ventilation systems, water tower freeze protection systems, and Hawkins
In Progress2015
NYPA White PlainsNYPA Facilities - Carbon Footprint & EO 88 Baseline StudyMULTIPLEMultiple
$130,000.00
0
Perform ASHRAE Level 1 audits at all NYPA facilities 
In Progress2015
PORT AUTHORITY OF NY AND NJPort Authority - Advanced Metering Infrastructure - Phase I Design/Engineering PhaseQUEENSSoutheastern
$4,197,353.14
0
Replace existing analog meters with new digital meters, that transmit data through the AMI system to a graphical user   interface that will improve energy management.
In Progress2015
PORT AUTHORITY OF NY AND NJPort Authority - Advanced Metering Infrastructure - Phase II MDSPMULTIPLEMultiple
$11,923,226.00
0
Phase 2: Upgrade the Port's utility purchasing and consumption data.
In Progress2015
PORT AUTHORITY OF NY AND NJPort Authority - World Trade Center Tower One - Fuel Cell and Energy EfficiencyNEW YORKSoutheastern
$27,216,767.00
6,759
Procure, deliver and commission a 1.2 Mw fuel cell power plant system including alternates and additions as may be requested and covered under the contract provisions. Finance engineering, design, and installation of the fuel cell power plant.
In Progress2015
1 - 100Next